Create a budget framework

Some Of the nominals and ledgers used in this topic may be different to those in your chart of accounts.

Use budgets to record estimates of income and expense based on future plans and objectives. You can then produce reports that compare the budget against actual performance, so you can find variances and, if needed, take action to correct them.

Good practice is to review budgets from previous years. Compare which figures you estimated accurately, which costs went over budget, and which, if any, you underspent. This helps you make the budget as accurate as possible.

You can create budgets manually or import them. This topic explains how to create your budget structure in IRIS Financials and add budget values manually.

You can also import a budget. For more information, go to Import budgets.

Before you start

Before you add a new budget, you have two options:

  • Create a new budget code: add a new budget code to the system. You can also use it as a revised budget or a forecast to compare against the initial budget for the year.

  • Update and add to an existing budget code: use the same budget code year on year. This is useful if you do not want numerous budget codes in the system, and it avoids changing the default budget in IRIS Purchasing at the start of each year.

Add the initial budget for each year to a master budget code. You can usually use your existing budget code. You can use the same code each year, because you save the budget against both a budget code and a year.

To create a new budget code, follow the steps in Create a budget code. If you are going to use an existing budget code, go to Enter budget values manually.

You can create a budget only for a year and period that exist. Check that you have set up the years and periods you want to enter the budget for. To check and add the years and periods you need, go to Maintenance, then select Periods. For more information, go to Add accounting periods manually.

Create a budget code

  1. Go to Maintenance, then select Budgets.

  2. The Budget Maintenance window opens and lists any existing budget codes. To add a new budget, select ADD NEW, then select BUDGET.
    If the new budget has the same settings as an existing budget, you can copy it. Select the existing budget in the list, select ADD NEW, then select BUDGET (COPY).

  3. In Budget, enter a code (maximum 12 characters). In Title, enter a title to help identify the budget. Then select SAVE. If you are entering a transactional budget, select Transactional.
    Do not use spaces or special characters in the budget code. Use capital letters, numbers, or both, for example BUDGETV2. You do not need to create a new code for each year, because you save budgets against both a budget code and a year.

    By default, the Access level for a budget is 3. To restrict access to the budget, increase this number. To change it, overwrite the number or use the up and down arrows to select the access level you need.

Enter budget values manually

  1. Go to Maintenance, then select Nominal Budget Details.

  2. The Nominal Budget Detail Maintenance window opens. The window title shows the year and the budget code. If needed, select CHANGE YEAR and CHANGE BUDGET to change them to the year and budget code you want to populate.

  3. You can apply budgets to several different ledger accounts (cost centres) on the same nominal, so you set the budget value for each account rather than for the nominal as a whole. Select the nominal you want to add the budget to, then select ACCOUNTS.

  4. The Nominal Account Budget Detail Maintenance window opens and lists the ledger accounts (cost centres). Select the account you need, then select EDIT.
    You must enter income as a minus figure, because income is a credit value. For example, -1,000 shows income against the specified nominal and account. Enter expenditure as a debit value.

  5. In the Balance column, enter the budget values for each period for the selected nominal and account. When you have entered all the budget details, select SAVE. Repeat this for all the nominals and accounts you need.

    The Reporting Suite has a Budget Matrix report, which gives an overview of the budget for any budget code. You can review it at any time to check your budget. To open the report, go to Modules, then select Reporting Suite. In the General Reports panel, select Budget Matrix.