Changing the Payrun Date

If you have opened the payrun and entered variable data, but later realised that the dates are wrong, you may re-date the payrun without losing the data input so far.

The start and end dates for the pay run and the date up until which SSP should be paid can be amended; this automatically recalculates the pay run based on the new dates.

  1. Click on the Payrun icon.

  2. Go to the Payrun menu and select Amend Payrun followed by Redate Payrun.

  3. The payrun dates screen will be displayed.

  4. Amend any dates as appropriate. Click OK to continue and redate the payrun.